Recoveries: Parking Garage

This project was an $18 million GMP project with general conditions, concrete and structural steel at cost.

AUDIT SCOPE

Review and analyze construction contracts with the Construction Manager, concrete and structural steel subcontractors; thorough review of payment applications and cost documentation at KBC offices.

KBC created Audit Issue Backcharges amounting to $764,396.

Major over-billed costs were:

Extra craft labor markup    $358,265.00
Billed wrong project    $136,126.00
Excessive Liability Insurance billings     $68,929.00
Over-billed supplier costs $41,471.00

KBC and our client performed negotiations and recovered $629,000.

Contact Kelly Business Consultants TODAY
and let our 50 years of experience reduce YOUR project costs!

Auditing the Entire Construction Project
We make a worthwhile financial contribution to each client’s bottom line
On-Going Monthly Audits
We identify over-billings at the earliest stage producing the maximum cost savings for our clients
Auditing Project Controls
We identify cost saving/prevention and cost-payment recoveries
Close Out Audits
We assist our clients in recovering three to five times our fee.