This project was a $110 million GMP Design Build project with general conditions, concrete and structural steel at cost.
Review and analyze construction contracts with the Construction Manager who self performed much of the work on a cost plus basis, thoroughly review payment applications, Change Orders and cost documentation at KBC offices and the office of the Construction Manager.
| Major over-billed costs were: | |
| Over-billed labor fringes of operators    | $397,397.00 |
| Duplicate materials or general conditions items  | $249,337.00 |
| Subcontractor over-billings | $183,964.00 |
| Labor FUTA and SUTA over-billed     | $161,130.00 |
| Overhead costs duplicated  | $181,132.00 |
| Non contract billable markups | $279,208.00 |
KBC and our client performed negotiations to recover $1,101,845 with another $876,412 under closed door settlement.