Recoveries: Manufacturing Plant

The project was a $65 million Cost Plus project.

AUDIT SCOPE

Review and analyze construction contracts with the Construction Manager and mechanical subcontractor; thoroughly review  payment applications and cost documentation at KBC offices and the office of the plumbing/mechanical subcontractor.

 

Major over-billed costs were:

Unsupported mechanical/control equipment    $103,005.00
Apprentices billed at journeyman rates   $84,226.00
Unsupported/undocumented labor $60,854.00

KBC and our client performed negotiations and recovered $394,535.

Contact Kelly Business Consultants TODAY
and let our 50 years of experience reduce YOUR project costs!

Auditing the Entire Construction Project
We make a worthwhile financial contribution to each client’s bottom line
On-Going Monthly Audits
We identify over-billings at the earliest stage producing the maximum cost savings for our clients
Auditing Project Controls
We identify cost saving/prevention and cost-payment recoveries
Close Out Audits
We assist our clients in recovering three to five times our fee.