The project was a $65 million Cost Plus project.
Review and analyze construction contracts with the Construction Manager and mechanical subcontractor; thoroughly review payment applications and cost documentation at KBC offices and the office of the plumbing/mechanical subcontractor.
Â
Â
| Major over-billed costs were: | |
| Unsupported mechanical/control equipment   | $103,005.00 |
| Apprentices billed at journeyman rates  | $84,226.00 |
| Unsupported/undocumented labor | $60,854.00 |
KBC and our client performed negotiations to recover $394,535.