Recoveries: Hospital

Hospital ResultsThis project cost $62 million based upon a GMP contract having general conditions and mechanical contracting at cost.

AUDIT SCOPE:

Review and analyze construction contracts with the Construction Manager and mechanical subcontractor; thoroughly review payment applications and cost documentation at the offices of the Construction manager and mechanical subcontractor.

 

 

Major over-billed costs were
“In-house store” material charges  $455,492.00
Sub-subcontractor sheet metal fees$101,304.00
Duplicated small tool charges$151,079.00
Machine rentals more than cost  $351,248.00
Excessive Liability Insurance billings$100,855.00
Various payroll over billings   $388,000.00

Our client performed negotiations to recover $1,130,000.